Why Plan – At the Correct Level of Detail

Home Lean ProjectsWhy Plan – At the Correct Level of Detail

Why Plan – At the Correct Level of Detail

Posted by Tom Richert Lean Projects
  • Share
  • Tweet

floor-plan-1474454_1280Builders will at times lament the quality of drawings given them to construct a building (yes, that really happens). Before throwing rocks, builders ought to be looking at the quality of their plans for constructing the project.

Construction plans built by first planners identifying thousands of detailed activities assembled in a critical path method are often about as useful as sheets of architectural details that are either too generic to be useful or unrelated to the project.

That is why Last Planner System phase plans and weekly plans need to consider the quality of detail included in both kinds of plans. Is the detail enough to inform project team members of the work to be accomplished at any given time during the week and following five weeks? Does the detail clearly show the handoffs between the work so the project team understands the promises being made as part of the planning?

And importantly – are phase plans and weekly plans being posted in the field? Those phase and weekly work plans are just as vital to the people constructing the building as the drawings!

Share this:

  • Click to share on X (Opens in new window) X
  • Click to share on Facebook (Opens in new window) Facebook

Related

Share
0

About Tom Richert

Tom is a frequent speaker, workshop facilitator, panel discussion presenter, and university guest lecturer on topics of collaborative productivity, team culture and alignment, lean management, and project leadership. He lives outside Boston with his wife. Their daughter is a stage management major at Ithaca College.

You also might be interested in

Weekly Coordination Meeting Plus Delta

Jan 6, 2017

Plus: Separating the project meeting for these two projects from that[...]

Leadership Group Meeting Plus Delta

May 11, 2018

PLUS: Progress on initiatives; Initiative updates are helpful and provide[...]

Weekly Coordination Meeting Plus Delta

Jan 6, 2017

Plus: The team has improved its use of weekly work plans;[...]

Contact Tom

Send an email and I'll get back to you within 12 hours.

Send Message

Recent Articles

  • How To Energize Decisionmaking: A Framework For Project Success
  • Designing For Success: How Early Efforts Drive Quality In Capital Projects
  • How to Use Percent Plan Complete to Deliver Projects Faster
  • How to Develop Awesome Internal Project Performance Coaching Results
  • Wiring Winning Projects in a Sizable Industry and Looming Workforce Decline

© 2025 · Tom Richert.

Prev Next
     

    Loading Comments...