Weekly Construction Coordination Meeting Plus-Delta

Plus: Removed constraints; New Percent Plan Complete graph; Foremen pointing to plans when explaining work for following week.

Delta: Finish meeting on time; Audit time spent on each agenda item to identify why meetings finish late; Request a foreman lead next week’s meeting.