Phase Pull Plan – Building Structure and Envelope

Home Plus-DeltaPhase Pull Plan – Building Structure and Envelope

Phase Pull Plan – Building Structure and Envelope

Posted by Tom Richert Plus-Delta
  • Share
  • Tweet

Plus: Organizing plan visually by building level was helpful; trade foreman and project manager input into plan is helpful.

Delta: Provide the team with more advance knowledge regarding flow strategy and level of detail required for plan; organize the relationships between tasks better; trades should bring the drawings they used for estimate takeoff to planning session.

Share this:

  • Click to share on X (Opens in new window) X
  • Click to share on Facebook (Opens in new window) Facebook

Related

Share
0

About Tom Richert

Tom is a frequent speaker, workshop facilitator, panel discussion presenter, and university guest lecturer on topics of collaborative productivity, team culture and alignment, lean management, and project leadership. He lives outside Boston with his wife. Their daughter is a stage management major at Ithaca College.

You also might be interested in

Lean Bootcamp Plus-Delta

Jun 10, 2015

Plus: Parade of Trades; Silent Squares; Attendance. Delta: Provide handouts[...]

Construction Team Weekly Coordination Meeting Plus-Delta

May 25, 2016

Plus: Air conditioning. Delta: All on agenda need to attend;[...]

STOP Celebrating Mediocrity!!

Sep 23, 2015

The words were right there in an email newsletter designed[...]

Contact Tom

Send an email and I'll get back to you within 12 hours.

Send Message

Recent Articles

  • How To Energize Decisionmaking: A Framework For Project Success
  • Designing For Success: How Early Efforts Drive Quality In Capital Projects
  • How to Use Percent Plan Complete to Deliver Projects Faster
  • How to Develop Awesome Internal Project Performance Coaching Results
  • Wiring Winning Projects in a Sizable Industry and Looming Workforce Decline

© 2025 · Tom Richert.

Prev Next